For the first two projects, Alstom will supply new runners for units C-1 and C-3 at the Beauharnois Generating Station. The third contract is for the Pointe du Bois Spillway Replacement Project.
Alstom’s North American Hydro headquarters and manufacturing facility in Sorel-Tracy, QC, will design, produce and deliver one new 47MW Francis turbine runner for unit C-1 of Hydro-Québec’sBeauharnois Generating Station.
Hydro-Québec has also exercised the option for five additional upgraded propeller runners including part refurbishment for unit C-3, which falls within the framework of an original contract the Quebec utility awarded Alstom in 2010.
The individual retrofit projects will increase electricity output by replacing old runners with new, more efficient designs that produce more electricity. The scheduled delivery date for unit C-1 is November 2013 and the first runner for unit C-3 under the option taken up by....Alstom bags three major hydro projects in Canada