The offshore oil platforms are part of the Clair Ridge project being developed by BP and its co-venturers, ConocoPhillips, Chevron, and Shell, and will use the latest technologies to enhance oil recovery and avoid environmental impact in the area near the UK’s Shetland Islands.
In addition to providing automation technologies, Emerson will serve as the project’s main automation contractor under a global agreement with BP. In this role, Emerson will provide automation services that include system engineering, installation, configuration, testing, and ongoing support.
The integrated Emerson solution will use Emerson’s PlantWeb™ digital plant architecture, including its DeltaV™ digital automation system, DeltaV SIS™ process safety system, and AMS Suite predictive maintenance software. The digital automation technologies will support BP’s Field of the Future® program for enhancing operating efficiency and oil recovery....
Emerson to provide safety systems for BP’s Clair Ridge project
Wednesday, May 30, 2012
TGE receives US$11.5 million grant for Apas Kiri geothermal project
Apas Kiri will be Malaysia's first geothermal energy development. It is expected to come online by early 2015 with a rated net capacity of 30MWs. Continental Energy owns a 10 percent stake in TGE.
The grant will be disbursed under the Facilitation Funds Agreement (FFA) by Bank Pembangunan Malaysia Berhad (BPMB), a development bank owned by the Malaysian Government and mandated to provide medium to long term financing to capital intensive development and infrastructure projects.
The proceeds of the grant are to be exclusively utilized by TGE to pay for costs associated with constructing access roads and making related infrastructure improvements involving the Apas Kiri geothermal power development....
TGE receives US$11.5 million grant for Apas Kiri geothermal project
The grant will be disbursed under the Facilitation Funds Agreement (FFA) by Bank Pembangunan Malaysia Berhad (BPMB), a development bank owned by the Malaysian Government and mandated to provide medium to long term financing to capital intensive development and infrastructure projects.
The proceeds of the grant are to be exclusively utilized by TGE to pay for costs associated with constructing access roads and making related infrastructure improvements involving the Apas Kiri geothermal power development....
TGE receives US$11.5 million grant for Apas Kiri geothermal project
First power module at Neal Hot Springs reaches mechanical completion
The total project is about 90 percent complete with aruound 65 percent of the US Dept of Energy project loan already drawn down to fund construction.
Mechanical completion of the first module marks the initiation of commissioning activities on various individual power plant components, controls and the related production and injection wellfield. Once these commissioning activities are complete, the power module will undergo acceptance testing, leading up to full module startup and continuous operation.
The second power plant module is expected to achieve mechanical completion around June 7, 2012 and the third module is slated to achieve mechanical completion by the end of June, 2012.
First power module at Neal Hot Springs reaches mechanical completion
Mechanical completion of the first module marks the initiation of commissioning activities on various individual power plant components, controls and the related production and injection wellfield. Once these commissioning activities are complete, the power module will undergo acceptance testing, leading up to full module startup and continuous operation.
The second power plant module is expected to achieve mechanical completion around June 7, 2012 and the third module is slated to achieve mechanical completion by the end of June, 2012.
First power module at Neal Hot Springs reaches mechanical completion