The total project is about 90 percent complete with aruound 65 percent of the US Dept of Energy project loan already drawn down to fund construction.
Mechanical completion of the first module marks the initiation of commissioning activities on various individual power plant components, controls and the related production and injection wellfield. Once these commissioning activities are complete, the power module will undergo acceptance testing, leading up to full module startup and continuous operation.
The second power plant module is expected to achieve mechanical completion around June 7, 2012 and the third module is slated to achieve mechanical completion by the end of June, 2012.
First power module at Neal Hot Springs reaches mechanical completion