Performance testing includes guaranteed output, capacity, reliability and continuous operation tests that the plant must pass to achieve both commercial operation under the PPA and substantial completion under the EPC contract.
The San Emidio power plant has undergone component commissioning during the past three weeks and has operated at generation levels of up to 9 megawatts net (12 megawatts gross).
During commissioning and performance testing, all power generated is sold under the PPA at a rate of $50 per megawatt-hour until commercial operation is achieved. Upon acceptance of commercial operation by NV Energy, the power rate will increase to $89.75 per megawatt-hour with a 1 percent annual escalation...
US Geothermal starts performance testing at San Emidio power plant